Influence of Client-Related Variations on Implementation of Kenya National Highways Authority Projects
DOI:
https://doi.org/10.70619/vol6iss2pp29-42-944Keywords:
Client Variations, Contingency Theory, Risk Management, Infrastructure Projects, ImplementationAbstract
Client‑related variations such as scope changes, specification modifications, delayed instructions, and financial constraints are a major source of delays and cost overruns in infrastructure projects. Globally, they account for 6-15% of cost escalations in Europe and up to 45% of schedule slippages in Asia. In Africa, systemic challenges including weak planning and financial constraints exacerbate these impacts. In Kenya, despite recent improvements - including 4.5% sector growth reported by KNBS in 2025 and clearance of a KShs.177 billion backlog in 2026 - client‑related variations remain a key disruptor of KeNHA road projects. A descriptive research design was employed, targeting 600 respondents across 50 ongoing KeNHA projects. A total of 443 valid responses were obtained (73.8% response rate). Data was collected using structured questionnaires and analyzed through descriptive statistics, regression models, and moderation analysis. Regression analysis revealed that client‑related varwereiations explained 60.3% of the variance in project implementation outcomes, with unclear scopes, delayed instructions, and financial constraints as key drivers. Moderation analysis confirmed that project risk management significantly reduced adverse effects, raising explanatory power from 57.3% to 88.9%. Client‑related variations significantly influence project implementation outcomes in KeNHA projects, but effective risk management frameworks can mitigate their disruptive effects. Embedding proactive risk identification, clear communication, and accountability mechanisms is essential for timely, cost‑effective, and quality delivery of road infrastructure, supporting Kenya’s broader economic growth and poverty reduction objectives.
References
Acebes, F., Pajares, J., Gúdel, R., & Martín-Cruz, N. A computational analysis of correlation and network structure effects on activity prioritization in project schedules. Available at SSRN 6149632.
African Development Bank (AfDB). (2020). Africa Infrastructure Development Index Report. Abidjan: AfDB. Retrieved from https://www.afdb.org
Alenazi, E., Adamu, Z., & Al-Otaibi, A. (2022). Exploring the nature and impact of client-related delays on contemporary Saudi construction projects. Buildings 12(7): 880.
Alnhari, A. A., & Qureshi, R. (2024). Unified external stakeholder engagement and requirements strategy. arXiv preprint arXiv:2409.05019.
Arain, F. M., Assaf, S., & Pheng, L. S. (2016). Causes of variation orders in construction projects. Journal of Construction Engineering and Management, 132(7), 563–571.
Burrell, G., & Morgan, G. (2017). Sociological paradigms and organizational analysis: Elements of the sociology of corporate life. Routledge.
Czarnigowska, A., & Tomczak, M. (2025). Construction cost contingency planning: An art or a science? In M. J. Skibniewski, M. Hajdu, & Ž. Turk (Eds.), Proceedings of the Creative Construction Conference 2025.
Donaldson, L. (2001). The contingency theory of organizations. Sage Publications.
Edward-Alikor, C., & Adiele, K. C. (2025). Assessing factors causing variations in building construction projects in Rivers State, Nigeria. International Journal of Social Sciences and Management Review, 11(5), 72–86.
Elbeltagi, I., & Dawood, M. (2021). Causes and effects of variation orders in Egyptian construction projects. International Journal of Construction Management, 21(5), 456–468.
Fatima, A., Mubin, S., & Masood, R. (2024). Risk-based integrated performance assessment framework for public-private partnership infrastructure projects. Organization, technology & management in construction: an international journal, 16(1), 251-274.
Fiedler, F. E. (1964). A contingency model of leadership effectiveness. Advances in Experimental Social Psychology, 1, 149–190.
Gatitu, J. N., Kabubo, C. K., & Ajwang, P. (2020). Approaches on mitigating variation orders in road construction industry in Kenya: The case of Kenya National Highways Authority (KeNHA). Engineering, Technology & Applied Science Research, 10(5), 6195–6199.
Gavamukulya, C. (2024). Variations in construction contracts. European Journal of Applied Science and Engineering Technology, 2(6), 197–199.
Ginsberg, A., & Venkatraman, N. (1985). Contingency perspectives of organizational strategy: A critical review of empirical research. Academy of Management Review, 10(3), 421–434.
Hanisch, B., & Wald, A. (2012). A bibliometric view on the use of contingency theory in project management research. Project Management Journal, 43(3), 4–23.
HKA. (2020). CRUX Insight Report: Global Construction Claims and Disputes. HKA Global. Retrieved from https://www.hka.com/crux
Jibrin, A. M., Muhammad, N. Z., & Labaran, Y. H. (2020). Evaluation of factors responsible for variation order in civil engineering projects: A clients’ perspective (a case study in Kano State, Nigeria). Evaluation, 7(5).
Kakw’u, F. M. (2024). Project Management Strategies and Performance of Public Private Partnership Road Infrastructure Projects in Nairobi City-County. Kenya (Doctoral dissertation, Kenyatta University).
Karanja, I. M., & Ruguru, F. (2023). Project management drivers and performance of road construction projects in Nairobi County, Kenya. International Journal of Social Science Management and Entrepreneurship, 7(2): 353–367.
Kenya National Bureau of Statistics. (2025). Economic Survey 2025. Nairobi: KNBS. ISBN: 978-9966-102-49-2. Retrieved from https://www.knbs.or.ke
Kenya National Highways Authority (KeNHA). (2023). Annual Report 2023. Nairobi: KeNHA. Retrieved from https://kenha.co.ke
Kenya National Highways Authority (KeNHA). (2024). Strategic Plan 2023–2027. Nairobi: KeNHA. Retrieved from https://kenha.co.ke
Kenya Roads Board. (2025). Annual Public Roads Programme (APRP) FY 2024/25. Nairobi: KRB. Retrieved from https://krb.go.ke
Koirala, M. P., Thapa, N., Giri, O. P., & Shah, R. (2025). Evaluation of variation orders on road construction projects in rural Nepal. Construction Economics and Building, 5(3), 311–338.
Lakmeeharan, K., Manji, Q., Nyairo, R., & Poeltner, H. (2020). Solving Africa’s infrastructure paradox: There is need and available funding, together with a large pipeline of potential projects—but not enough money is being spent. McKinsey & Company: Capital Projects & Infrastructure.
Mbogori, K. N., & Mutuku, M. (2025). Risk Management Strategies and Performance of Selected Road Construction Projects in Kenya.
Moore, M. A., & Vining, A. R. (2023). PPP performance evaluation: the social welfare goal, principal–agent theory and political economy. Policy Sciences, 56(2), 267-299.
Morgan, G. (1997). Images of organization. Thousand Oaks, CA: Sage Publications.
Mugenda, O. M., & Mugenda, A. G. (2003). Research Methods: Quantitative and Qualitative Approaches. Nairobi: Acts Press.
O’Rourke, J., Coughlan, C., Spillane, J. P., & Bradley, J. (2025). The impact of variations on the project programme in the construction industry. In Proceedings of the Sustainable Ecological Engineering Design Conference (pp. 283–294). University College Dublin.
Sing, M. C. P., Ma, Q., & Gu, Q. (2025). Improving cost contingency estimation in infrastructure projects with artificial neural networks and a complexity index. Applied Sciences, 15(7), 3519.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Francis Benedict Ondiek, Antony Sije, Yusuf Muchelule

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.