The Effects of Financing on Completion of Government Road Projects: A Case of Kenya National Highway Authority

Authors

  • Patricia Aponga Chibole Kenyatta University
  • Patrick Mbataru Kenyatta University

DOI:

https://doi.org/10.70619/vol3iss2pp40-47

Keywords:

Financing, Completion of Government Road Projects, Kenya National Highway Authority

Abstract

Maintaining steady completion of road construction projects in the government of Kenya has been an issue of concern to the government, stakeholders, and contractors. Therefore, there have been numerous cases of delays and non-completion of projects which have contributed to irreparable loss to the government and the economy as a whole. Studies done on road construction tend to concentrate on the success of the projects, to add more knowledge, this study sought to address the problem of completion of government road construction projects. This study sought to fill this gap by analyzing the effects of financing on the completion of government road construction projects in Kenya with special reference to the Kenya National Highway Authority. This research adopted a descriptive approach and the target population was composed of 240 management staff of the Kenya National Highway Authority. The researcher used a stratified random sampling procedure to select a sample size of 72 respondents. Quantitative data was collected using questionnaires and analyzed by the use of descriptive statistics and regression analysis. Findings revealed that financing had a positive and significant effect on the completion of government road projects. The project’s budget is crucial and it has an influence in all areas of both project planning as well as implementation. It is crucial to keep track of expenses for various work packages and total costs in a project. The road project financier should produce a clear schedule of funds on all project cycles and have devoted qualified staff members who are capable of creating scenarios of effective timeliness and implementation. This makes timely funding and project planning easier to manage, and it can be useful for projects similar to the current project.

Author Biographies

Patricia Aponga Chibole, Kenyatta University

Public Policy and Administration Department

Patrick Mbataru, Kenyatta University

Public Policy and Administration Department

References

Aibinu, A.A., Jagboro. G.O. (2017). The effects of construction delays on project delivery in Nigerian Construction Industry, International Journal of Project Management, Vol. 20, pp. 593-599.

Alaghbari, W. E., Razali A. Kadir, M., Salim, A., & Ernawati. (2017). The significant factors causing delays in building road construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192-206.

Alfred, C. (1980). "Construction Cost Control by the Owner," ASCE Journal of the Construction Division, Vol. 106, No. 4, December, 1980, pg. 444

Al-Homidan, S., Ghanam, R.A. and Tatar, N. (2018). On a generalized diffusion equation arising in petroleum engineering. Advances in Difference Equations Journal. Springer International Publishing.

Bennett D.F.H. & Gordon R.W. (2014) Project profile broad walk house case study report. British Cement Association. Wexham Springs, United Kingdom.

Chism, N., Armstrong, G. (2015). Project delivery strategy: getting it right. KPMG International, pp.1-24.

Dlamini, Mcebisi & Cumberlege, R. (2021). The impact of cost overruns and delays in the construction business. IOP Conference Series: Earth and Environmental Science. 654. 012029. 10.1088/1755-1315/654/1/012029.

Fugar, Frank & Agyakwah-Baah, Adwoa. (2010). Delays in Building Construction Projects in Ghana. Australasian Journal of Construction Economics and Building. 10. 10.5130/ajceb.v10i1/2.1592.

Ganiyu, Bashir & Zubairu, Ibrahim. (2010). Project cost prediction model using principal component regression for public building projects in Nigeria. J Build Perform. 1.

Hussin, A.A., Omran, A. (2016). Implication of non-completion projects in Malaysia. ACTA Technica Corviniensis-Bulletin of Engineering, University Polytechnic Timisoara. Romania.

Kagiri, D. and Wainaina, G. (2018). Time and Cost Overruns in Power Projects in Kenya: A Case Study of Kenya Electricity Generating Company Limited, Nairobi

Karimi, R.B. (2018). Factors which are Critical in Project Cost Overruns: A Case Study of Ministry of Water Resources Projects, Unpublished MBA Thesis, University of Nairobi.

Kikwasi, G.J. (2017). Causes and Effects of Delays and Disruptions in Road Construction Projects in Tanzania, Australasian Journal of Construction Economics and Building, Conference Series, (2) 52-59.

Kumaraswamy, Mohan & Dissanayaka, Sunil. (2010). Linking procurement systems to project priorities. Building Research & Information. 26. 223-238. 10.1080/096132198369832

Morris, S. (2014). Cost and Time Overruns in Public Sector Projects, Economic and Political Weekly, Nov. 24, Vol. XXV, No. 47, pp. M154 -168.

Msafiri, A. S. (2015). An Investigation into Factors Causing Delays in Road Construction Projects in Kenya. American Journal of Civil Engineering, Vol. 3(3), 51-63.

Olatunji, A. A. (2015). Influences on construction project delivery time. (PhD. thesis). Nelson Mandela Metropolitan University, Eastern Cape, South Africa.

Downloads

Published

2023-11-13

How to Cite

Chibole, P. A. ., & Mbataru, P. . (2023). The Effects of Financing on Completion of Government Road Projects: A Case of Kenya National Highway Authority. Journal of Public Policy and Governance, 3(2), 40–47. https://doi.org/10.70619/vol3iss2pp40-47

Issue

Section

Articles